Friday, May 2, 2025

PJM Interconnection: 51 Generation Projects, 9.3 GW To Move Forward to Address Near-Term Electricity Demand Growth-- 39 Upgrades, 12 New Construction

On May 2, the
PJM Interconnection announced it has selected 51 projects that can come online quickly and provide more than 9,300 MW of reliable capacity through the Reliability Resource Initiative.

The projects consist of 39 uprates and 12 new construction proposals.  [PJM will post a list of the projects and locations on May 6.]

The uprates apply to existing natural gas (1.978 GW), nuclear (496 MWe), coal and onshore wind resources. 

Of the new projects, half are gas (6.143 GW), five are batteries (2.275 GW) and one is nuclear (887MWe). 

The uprates total 2,108 MW of unforced capacity (UCAP), or the amount of energy a resource can be expected to provide during times of highest system reliability risk. 

The new projects would contribute 7,253 MW of UCAP, for a combined total of 9,361 MW.

Most of the projects, or 90%, are expected to be online by 2030. All are projected to be online by 2031. 

The Reliability Resource Initiative (RRI) is a one-time opportunity for shovel-ready resources that have short lead times to construction and operation and can most effectively contribute to reliability.

The projects were chosen from 94 applicants using a weighting process that assigned the most value to UCAP and in-service date, followed by Effective Load Carrying Capability (which values a resource’s contribution to reliability) and additional consideration for locating in zones in greatest need of generation.

PJM originally planned to limit the number of projects in the initiative to 50, but a tie in the weighted scoring system for the last two projects resulted in 51 projects being selected.

Process Moves Forward

The Federal Energy Regulatory Commission in 2022 approved PJM’s reforms that moved the interconnection process from a “first-come, first-served” system of managing new generation projects to a “first-ready, first-served” method with milestones and progress payments designed to weed out speculative projects.

PJM is moving toward completion of the transition period of the reformed interconnection process, which has thus far produced 18,000 MW worth of projects with signed interconnection agreements through PJM’s Fast Lane, for projects with lesser impact on the system. 

Those are among approximately 47,000 MW in projects that have completed PJM’s interconnection process and are free to move to construction and operation.

The projects that are part of the Reliability Resource Initiative will be studied as part of the final transition phase of PJM’s interconnection process reform. 

In addition to the RRI projects, PJM will complete processing on approximately 62,000 MW projects in 2025 and 2026.

PJM’s new Cycle process for projects seeking to interconnect with the system will begin in spring 2026, with a process time of one to two years.

Bringing More Generation Online

As new generation comes online more efficiently through these reforms, the demand for electricity and retirement of generators continues to outpace the addition of new generation. 

For the past several years, PJM has acted on multiple fronts to mitigate the risk of having inadequate generation resources to serve rapidly increasing electricity demand. 

These actions include--

-- Automation – Additional automation in the interconnection process, along with increased staffing over the past several years, has improved quality while reducing the backlog by 60%. PJM on April 10 also announced a multiyear collaboration with Google and Tapestry to deploy AI-enhanced tools to further streamline PJM’s planning process for connecting new generation resources to the grid.

-- Surplus Interconnection Service – PJM obtained FERC approval to streamline the use of the unused portion of interconnection service for facilities that cannot or do not operate continuously, every hour of every day, year-round (such as adding battery storage to a renewable site).

-- Capacity Interconnection Rights Transfer – A reform package endorsed by PJM stakeholders and currently pending review by FERC would facilitate an expedited interconnection process for a replacement resource seeking to use the capacity interconnection rights of a retiring resource.

PJM also is urging states to work with developers to help get generation constructed once it has cleared PJM’s study process.

PJM Interconnection ensures the reliability of the high-voltage electric power system serving 67 million people in all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia, West Virginia and the District of Columbia. 

Click Here for PJM’s announcement.

NewsClip:

-- PennLive Letter: Market Competition In PJM Is Solving Pennsylvania’s Energy Challenges - By Glen Thomas, Former Chair, PA Public Utility Commission [PJM Picks 51 Energy Projects]

Resource Links:

-- PUC Hearing On Data Center Growth Impacts Finds 30-40% Of Utility Demand Could Be From Data Centers; Concerns About Stranded Costs; Major Commitments To Net-Zero Carbon Emissions Energy Use

-- PUC House Budget Hearing: We Aren’t Going To Build Our Way Out Of Electric Generation Shortfalls On PJM Grid; We Need To Diversify Our Generation Sources   [PaEN]

-- PUC Invites Stakeholder Comments On The Issue Of The Adequacy Of Electricity Supplies In Pennsylvania  [Background On Issue]  [PaEN]

-- 30 Stakeholder Comments Received By PUC On Adequacy Of Electricity Supplies In Pennsylvania; Increasing Natural Gas Power Plant Reliability To 90-95% Would Mean No Imminent Capacity Problem  [PaEN]

-- Gov. Shapiro Launches Legislative Push for 'Lightning Plan’ To Build More Energy Projects, Speed Up Permitting, Lower Costs, Create Jobs For Pennsylvanians [PaEN]

-- Pennsylvania’s Electric Grid Is Dependent On One Fuel To Generate 59% Of Our Electricity; Market Moving To Renewables + Storage  [PaEN]

-- Gov. Shapiro Reaches Agreement With PJM To Prevent Unnecessary Price Hikes And Save Consumers Over $21 Billion On Utility Bills [PaEN]

-- PA Senate Republican Leader: ‘Every Consumer Of Electricity In This Commonwealth Is Going To Pay More;’ ‘What You’re Going To Face Is Going To Be Really Unpleasant’  [PaEN]

-- PJM Electricity Auction Price 9 Times Higher Than Previous Auction-- $269.92/MW-Day For 2025/26 Delivery Compared To $28.92/MW-Day In 2024-25; Extreme Weather Risk Big Factor  [PaEN]

Related Articles This Week:

-- DEP Received Air Quality Permit For 4.6 Gigawatt Homer City Generation Natural Gas Power Plant For Data Center In Indiana County  [PaEN] 

-- DEP Releases 2024 Climate Change Action Plan Update; 2024 Climate Impacts Assessment Report [PaEN] 

-- New Interactive Map Highlights Federal Clean Energy Investments In Pennsylvania  [PaEN]

-- PUC: Storm Recovery Moving Ahead, But Work Remains: 136,000 Customers Remain Without Power  [PaEN] 

NewsClips:

-- The Allegheny Front: Renewables Generate More Electricity Than Coal In PJM Regional Grid

-- WESA: Double The Solar Energy Coming Soon To Pittsburgh Airport

-- Post-Gazette - Anya Litvak: Duquesne Light Celebrates Its First Solar Power Agreement, For The Second Time 

-- Tribune-Democrat: PA House Republican Leader Says Lack Of Energy Development In PA Risks Economy, Power Grid [PDF of Article

-- PA Reps. Nelson, Mullens, Barton Announce Legislation To Accelerate Data Center Permitting 

-- WITF - Rachel McDevitt: Pennsylvania Weighs How To Manage Power-Hungry Data Centers

--  TribLive: Proposed TECfusions Data Center To Use 2 Gigawatts Of Natural Gas-Fired Electric Generation In First Phases [‘No Health Effects’ To The Community From Burning Fossil Fuels]

-- Utility Dive: Exelon Data Center Projects Pipeline Doubles To 36 GW Since Year-End 

-- PA Capital-Star: Nuclear Energy Growth In PA, Other States Need Federal Action

-- Floodlight.org: Transmission Line Conflicts Ahead As A.I. Drives US Electricity Demand  

-- Utility Dive: 9 Northeast States Seek Electric Transmission Proposals To Connect PJM, ISO-NE, New York 

-- EPA Issues Clarification Of Hazardous Air Pollutant Rules On Reciprocating Internal Combustion Engines To Help A.I. Data Centers 

-- Utility Dive: Midcontinent Grid Operator Reports Summer Electricity Prices Jump To $666.50/MW-day As Power Supplies Shrink, Surplus Capacity Fell [Last PJM clearing price for 2025-26 delivery was $269.92 MW-day, 933% higher

[Posted: May 2, 2025]  PA Environment Digest

No comments :

Post a Comment

Subscribe To Receive Updates:

Enter your email address:

Delivered by FeedBurner